On July 29, DKFW completed the construction period and received a Permit to Operate, and on August 28 it obtained …
Continue reading “August 2022”
DKFW has completed the construction period, and in June we applied for an Operating Permit. The turbines have already produced …
Continue reading “June 2022”
All turbines have successfully completed the Trial Run which is a test involving uninterrupted operation for 240 hours. The site …
Continue reading “May 2022”
Mechanical installation of the remaining 2 turbines has been completed and they have been connected to the grid. Currently, all …
Continue reading “April 2022”
Mechanical installation of 4 out of 6 turbines was completed. On 24 March, ENERGA-OPERATOR SA received the Temporary Use Permit, …
Continue reading “March 2022”
On 14th of February delivery and installation of VESTAS V126 wind turbines with a capacity of 3.45MW each started. A …
Continue reading “February 2022”
The last documents required by EOP for ESO application have been delivered. Last elements of the turbines have arrived to …
Continue reading “January 2022”
An application was submitted to ENERGA-OPERATOR SA (EOP) for permission to apply for EON voltage at GPO 30/110kV (Main Receiving …
Continue reading “December 2021”
Construction and power engineering works related to the construction of GPO and MV cable lines have been completed. Acceptance documentation …
Continue reading “November 2021”
Work is underway on the construction of temporary road elements necessary for the transportation and assembly of the wind turbines. …
Continue reading “October 2021”