Work is underway on the construction of temporary road elements necessary for the transportation and assembly of the wind turbines. …
Continue reading “October 2021”
The last foundation concreted!!! On September 29th, on the occasion of the completion of the concreting of all foundations, a …
Continue reading “September 2021”
The first 2 foundations of T1 and T6 power plants were concreted in, using almost 800m3 of concrete and 115t …
Continue reading “August 2021”
Excavations are complete and 5 sections of concrete foundations are in place. Works are in progress on the elevations of …
Continue reading “Five trenches ready”
Piling at 5 sites is complete. Piling work on T3 will begin after the swallows nesting season. A further 3 …
Continue reading “Piling almost complete”
Swallows have halted construction. Vertical slopes are a favorite nesting and egg-laying site for bank swallows. The birds took advantage …
Continue reading “Swallows liked the construction”
All the roads are ready and excavation has begun at 2 sites ready for piling. Each foundation uses about 400m3 …
Continue reading “Completion of road works”
DKFW has signed a loan agreement to finance the project. DNB and the Danish Export Credit Agency EKF have agreed …
Continue reading “Signing of the loan agreement”
50% of the crushed aggregate road surface has been laid. Due to the weak bearing capacity of the soil, each …
Continue reading “Aggregate roads half finished”
Road stabilization is complete. Walls are being constructed at the GPO building.